EICR codes explained: C1, C2, C3 and FI for contractors

An EICR's outcome turns on four codes. Here is what each means, what Amendment 4 changed in 2026, how often commercial buildings need inspecting, and how to turn the observations into remedial work.

By PPMdesk
Share this article

An Electrical Installation Condition Report (EICR) records the condition of an existing installation against BS 7671. Most of it is a schedule of inspections and test results, but the part the client reads is the list of observations, each with a classification code, and the overall assessment: satisfactory or unsatisfactory.

For a contractor, the codes matter twice: they decide whether the report is satisfactory, and they are the remedial work the inspection has found.

The four codes

CodeMeaningOutcomeWhat normally follows
C1Danger present. Risk of injury. Immediate remedial action required.UnsatisfactoryMade safe on the day (isolated or fixed), the client told before you leave
C2Potentially dangerous. Urgent remedial action required.UnsatisfactoryA remedial quote, as soon as possible
C3Improvement recommended.Does not affect the outcomeOptional work; quote if the client wants it
FIFurther investigation is advised.Does not affect the outcome (since Amendment 4)A price to investigate, which may turn up a C1 or C2
C1, C2 and C3 wording as on the BS 7671 model forms. FI wording and outcome rules from BS 7671:2018+A4:2026.

What Amendment 4 changed

BS 7671:2018+A4:2026 changed how FI works. Before, FI meant "further investigation required without delay", and in practice many inspectors treated an FI like a C2, marking the report unsatisfactory. Amendment 4 decouples C3 and FI from C1 and C2: only C1 and C2 make a report unsatisfactory, and FI now reads "further investigation is advised". The IET's own commentary adds that it should not be necessary to use FI in most circumstances.

Satisfactory or unsatisfactory

The overall assessment is unsatisfactory if there is any C1 or C2 observation. It stays unsatisfactory until the remedial work is done; the inspector does not change the original report. Most contractors issue a minor works or electrical installation certificate for the remedial work, and the client keeps it with the EICR as proof the observations were dealt with.

A report with C3s only is satisfactory. C3s are worth raising with the client anyway: they are often the next round of work, and a client who is told about them now trusts the next quote more.

How often commercial buildings need an EICR

There is no single legal interval for commercial premises. The Electricity at Work Regulations 1989 require installations to be maintained so as to prevent danger, and the usual benchmark is the maximum periods recommended in the IET's Guidance Note 3:

PremisesMaximum period between inspections
Offices, shops and other commercial premises5 years
Schools and other educational establishments5 years
Hospitals5 years
Industrial premises3 years
Leisure complexes and places of public entertainmentShorter, typically every year
The inspector can recommend a shorter interval on the report, based on the installation's condition and use. That date, not the table, is the one to plan for.

Turning codes into work

The commercial risk in an EICR is not the inspection; it is the C2 that sits in a PDF for three months because nobody turned it into a quote. A few habits fix most of it:

  1. Quote every C2 within a week. The client needs it fixed to make the installation satisfactory, and the longer it waits the more likely someone else quotes it.
  2. Price FIs as investigation, not as fixes. The FI says you don't yet know what's wrong. Quote the time to find out, and the fix separately once you do.
  3. Group observations by site. One quote per site with every C2 and FI on it is easier for the client to approve than six separate ones.
  4. Offer the C3s, separately. Don't bury optional work in the urgent quote; it slows the approval of both.
  5. Diarise the next inspection. Put the next due date on the site with a reminder, so the re-inspection is yours, not the next contractor's.

How PPMdesk handles it

PPMdesk does not produce the EICR itself; your engineers keep using their certification software. Around it: an EICR visit sheet records the outcome and the number of C1s, C2s, C3s and FIs, and the engineer reports each C2 or FI from the job on their phone, with photos and a price, and they arrive in Faults found by site. Tick them and they become one quote at cost plus your markup, which the client accepts online with their PO. The finished EICR PDF is filed on the site with its next due date, and shows on Today's list 30 days before it is due. How PPMdesk works for electrical contractors.

Frequently asked questions

Does an FI code make an EICR unsatisfactory?

Not since BS 7671:2018+A4:2026. Amendment 4 decoupled FI and C3 from C1 and C2, so only C1 and C2 observations make a report unsatisfactory. Under earlier editions, an FI usually did.

What is the difference between C1 and C2?

C1 means danger is present now and needs immediate action, so the inspector makes it safe or isolates it before leaving. C2 means potentially dangerous: not a danger yet, but it could become one, so it needs urgent remedial work.

Is a C3 a fail?

No. C3 means improvement recommended. A report with only C3 observations is satisfactory.

How often does an office need an EICR?

IET Guidance Note 3 recommends a maximum of five years for commercial premises such as offices and shops. The inspector may recommend a shorter interval on the report, and that recommendation is the one to follow.

Sources

Checked on 5 November 2026. If anything here is out of date, tell us and we will correct it.

See how PPMdesk works for electrical contractors

See it with your own jobs.

Start a free trial and bring your sites, units and contractors in from a spreadsheet. Or book a demo and we will show you with your own jobs.

  • 14-day free trial
  • No card needed
  • Cancel anytime